The Puerto Rico Department of Housing (PRDOH) has been designated by the Government of Puerto Rico as the agency responsible for administering CDBG-DR funds in close collaboration with the Central Office of Recovery, Reconstruction and Resilience (COR3). Under the commitment to administer the Funds in an efficient and transparent manner, PRDOH built its “Action Plan” to govern the recovery and reconstruction of the Island, after receiving multi-sector recommendations.
Draft Action Plan for Program Administrative Costs CDBG-DR Earthquakes & Storm Allocation
Draft Action Plan.
Posted on 05/04/2022
Action Plan Amendment 8 (Nonsubstantial Amendment): Effective on February 25, 2022
Submitted to HUD on February 18, 2022
Posted on 02/25/2022
The Action Plan is a document that defines how the emergencies of the humanitarian needs of the residents of the Island will be addressed, at the same time, develops and implements an effective recovery after the passage of hurricanes Irma and María. This document includes an analysis of the first calculation of damages and reports on the preliminary design of the 19 initial programs that will meet the urgent needs of Housing, Planning, Economic Recovery and Infrastructure.
In order to maintain full transparency of information on the disbursement of federal CDBG-DR funds, the Action Plan is available to the public through the website: www.cdbg-dr.pr.gov
The Action Plan was approved by the U.S. Department of Housing and Urban Development (HUD) on July 29, 2018. However, amendments are constantly being made to enforce the regulations issued by HUD.
The Action Plan brings together the strategies that will be used by the PRDOH to promote the recovery of the Island through the implementation of economic and social assistance programs in five sectors: Planning, Housing, Economy, Infrastructure and Multi-sector. Through the Action Plan, the Government of Puerto Rico will direct the implementation of the CDBG-DR Funds in order to mainly support recovery, reconstruction, economic revitalization and housing development initiatives.
*Date format mm/dd/yyyy.
Document Name | |||
---|---|---|---|
Draft Action Plan for Program Administrative Costs CDBG-DR Earthquakes & Storm Allocation |
05/04/2022 | Draft Action Plan. | View Details |
CDBG-DR Action Plan for the Electrical Systems Enhancements: Effective on March 25, 2022 |
03/31/2022 | Final version partially approved by HUD.View Projections | View Details |
Action Plan Amendment 8 (Nonsubstantial Amendment): Effective on February 25, 2022 |
02/25/2022 | Submitted to HUD on February 18, 2022View Projections | View Details |
CDBG-DR Action Plan for the Electrical Systems Enhancements |
01/27/2022 | Revised draft submitted to HUD for evaluation and final approvalView Projections | View Details |
Action Plan Amendment 7 (Substantial): Effective on November 5, 2021 |
11/09/2021 | Final version approved by HUD.View Projections | View Details |
Action Plan Amendment 7 (Substantial Amendment) |
11/09/2021 | Revised draft submitted to HUD for evaluation and final approvalView Projections | View Details |
Power Grid Action Plan: Draft for Public Comment – November 8, 2021 |
11/08/2021 | Draft Action Plan for Public Comments | View Details |
Action Plan for the 2019-2020 Earthquakes Recovery Response (DR-4473-PR) |
09/30/2021 | Final version approved by HUD on September 23, 2021.View Projections | View Details |
CDBG-DR Action Plan Amendment 7 (Substantial) |
08/06/2021 | Public comment period: August 6, 2021 – September 6, 2021.View Projections | View Details |
DRGR MIT Action Plan – Reviewed and Approved 06-21-2021 |
06/28/2021 | Final version approved by HUD on June 21, 2021View Projections | View Details |
CDBG-MIT Action Plan: Effective on April 19th, 2021 |
04/26/2021 | Final version approved by HUD on April 19, 2021View Projections | View Details |
Action Plan Amendment 6 (Nonsubstantial): Effective on March 15, 2021 |
03/16/2021 | Submitted to HUD on March 8, 2021.View Projections | View Details |
CDBG-MIT Action Plan: Effective on February 1, 2021 |
03/05/2021 | Final version partially approved by HUD.View Projections | View Details |
Action Plan Amendment 5 (Substantial): Effective on February 5, 2021 |
02/18/2021 | Final version approved by HUDView Projections | View Details |
Action Plan Amendment 5 (Substantial Amendment) |
12/08/2020 | Revised draft submitted to HUD for evaluation and final approvalView Projections | View Details |
CDBG-MIT Action Plan |
12/04/2020 | Draft submitted HUD for evaluation and final approval.View Projections | View Details |
CDBG-MIT Action Plan |
09/21/2020 | Draft published for public commentView Projections | View Details |
Action Plan Amendment 5 (Substantial Amendment) |
09/10/2020 | Draft published for public comment on 2020-09-10View Projections | View Details |
Action Plan Amendment 4 (Substantial Amendment): Effective on August 17, 2020 |
09/03/2020 | Final version approved by HUDView Projections | View Details |
Action Plan Amendment 4 (Substantial Amendment): Revised draft submitted to HUD for evaluation and final approval. |
07/11/2020 | Submitted to HUD on July 9, 2020View Projections | View Details |
Action Plan Amendment 4 (Substantial Amendment) |
03/31/2020 | Draft published for public comment on 2020-03-31View Projections | View Details |
Action Plan Amendment 3 (Nonsubstantial Amendment): Effective on February 24, 2020 |
02/24/2020 | Final version submitted to HUD on February 17, 2020View Projections | View Details |
Action Plan Amendment 2 (Nonsubstantial Amendment): Effective on August 23, 2019 |
08/23/2019 | Final version submitted to HUD on August 16, 2019View Projections | View Details |
Action Plan Amendment 1 (Substantial Amendment): February 28, 2019 |
03/20/2019 | Final version approved by HUD.View Projections | View Details |
Action Plan Amendment 1 (Substantial Amendment): November 18, 2018 |
11/09/2018 | Revised draft submitted to HUD for evaluation and final approval.View Projections | View Details |
Action Plan Amendment 1 (Substantial Amendment): September 21, 2018 |
09/21/2018 | Draft published for comments from the general public.View Projections | View Details |
Action Plan: July 29, 2018 |
08/30/2018 | Final version approved by HUD.View Projections | View Details |
Action Plan: June 14, 2018 |
06/26/2018 | Revised draft submitted to HUD for evaluation and final approval.View Projections | View Details |
Action Plan: May 10, 2018 |
05/09/2018 | Draft published for comments from the general public.View Projections | View Details |